UKBS Plc Civil and Structural Design Project

Projects - Civil and Structural Design Project

Brittanic operate a timber yard covering an area of 10 hectares on reclaimed land immediately behind the River Humber Flood Bank.

Our brief included:

  1. Site Investigation to this landfill site.
  2. Design of a full drainage scheme with 100% (final) impermeable area.
  3. Timber Storage Building Design.

UKBS PlcL Civil and Structural Design Project - Drainage SystemThe design of the drainage scheme relied on the utilisation of an outfall for surface water into the River Humber. As the river bank in this area is a Site of Special Scientific Interest (SSSI) our negotiations were extensive and agreements had to be reached with English Nature, the Environment Agency and MAFF relating to the design and construction of the outfall structure on the River Bank.

UKBS PlcL Civil and Structural Design Project - Timber Storage BuildingThe Timber Storage Building was designed to accommodate high racking to carry packs of timber in a dry but ventilated environment. The building provides 7000m2 of covered area and consists of a steel portal frame on concrete pad foundations.

Contract Details

  • Client: Brittanic Timber Limited
  • Value: £500,000
  • Civil & Structural Design: UKBS Plc
  • Building Designer: Gammond Evans Crichton Limited
  • Contractor: High Oak Construction